Sample Practice Questions

Try these 10 sample questions from the Qualifying Builder (QB) Exam practice bank. Each includes the answer and explanation. Continue with the interactive practice above to review the full question set.

  1. 1When plans are required with a Minnesota residential permit application, how must the construction documents present the proposed work?

    1. A. Clearly and with enough detail to show code compliance
    2. B. As a preliminary narrative without dimensions
    3. C. Only as a contractor's material takeoff
    4. D. Only as an owner's room list

    Answer: A

    Explanation: Minnesota Rule 1300.0130 requires construction documents to be "of sufficient clarity" to show the proposed work and its code compliance.

    Reference: 1300 - MN Rules Chapter — Minn. R. 1300.0130, subp. 1

  2. 2A new dwelling is being framed. From which places must a continuous and unobstructed egress path be provided?

    1. A. Only sleeping rooms
    2. B. Only the first story
    3. C. Only finished rooms
    4. D. All portions of the dwelling

    Answer: D

    Explanation: Section R311.1 requires a continuous and unobstructed path of vertical and horizontal egress travel from all portions of the dwelling. The governing code "is incorporated by reference and made part of the Minnesota State Building Code".

    Reference: 1309 - MN Rules Chapter — Section R311.1, Means of egress

  3. 3Which referenced standard controls the maximum cementitious-material percentages in concrete exposed to deicing chemicals?

    1. A. ASTM D3679
    2. B. ACI 318 Section 19.3.3.4
    3. C. ASTM D226 Type I
    4. D. CPA/ANSI A135.6

    Answer: B

    Explanation: Section R402.2 requires those percentages to not exceed the percentages of the total weight of cementitious materials specified in Section 19.3.3.4 of ACI 318. The governing code "is incorporated by reference and made part of the Minnesota State Building Code".

    Reference: 1309 - MN Rules Chapter — Section R402.2, Concrete

  4. 4When No. 15 asphalt felt is used as the exterior wall water-resistive barrier, what minimum horizontal lap is required?

    1. A. 2 inches
    2. B. 1 inch
    3. C. 4 inches
    4. D. 6 inches

    Answer: A

    Explanation: Section R703.2 requires the upper layer to lap the lower layer not less than 2 inches. The governing code "is incorporated by reference and made part of the Minnesota State Building Code".

    Reference: 1309 - MN Rules Chapter — Section R703.2, Water-resistive barrier

  5. 5Which orientations may be used when applying gypsum board to framing members?

    1. A. Only at 30 degrees
    2. B. Only at 45 degrees
    3. C. Only at 60 degrees
    4. D. At right angles or parallel

    Answer: D

    Explanation: Section R702.3.5 states: Gypsum board and gypsum panel products shall be applied at right angles or parallel to framing members. The governing code "is incorporated by reference and made part of the Minnesota State Building Code".

    Reference: 1309 - MN Rules Chapter — Section R702.3.5, Application

  6. 6A licensed residential contractor renovates a pre-1978 dwelling in a way that disturbs regulated painted surfaces. What additional compliance is required?

    1. A. Compliance with Minnesota's lead certification requirements
    2. B. Only a municipal electrical permit
    3. C. Only a new-home warranty filing
    4. D. An assumed-name publication

    Answer: A

    Explanation: Under the statutory heading "Pre-1978 structures," Minn. Stat. § 326B.805 requires qualifying renovation work to comply with the lead-certification provision in § 326B.106, subd. 14.

    Reference: Minnesota Statutes 2025, Chapter 326B — Minn. Stat. § 326B.805, subd. 1a

  7. 7To win an insured residential roofing job, may a contractor promise to pay the homeowner's insurance deductible?

    1. A. Yes, if disclosed after completion
    2. B. Yes, if called an advertising allowance
    3. C. No, the contractor may not pay or promise to pay the deductible
    4. D. Yes, if the insurer is not told

    Answer: C

    Explanation: Minn. Stat. § 325E.66 prohibits promising to pay an "applicable insurance deductible" as an inducement to the insured.

    Reference: Minnesota Statutes 2025, Chapter 325E — Minn. Stat. § 325E.66, subd. 1

  8. 8When the DLI commissioner believes a construction-code licensing violation has occurred, which enforcement instrument may direct the violation to stop or be corrected?

    1. A. A warranty waiver
    2. B. An administrative order
    3. C. A post-loss assignment
    4. D. A lien statement

    Answer: B

    Explanation: Minn. Stat. § 326B.082 authorizes the commissioner to issue an administrative order requiring the violation to be corrected; the commissioner "may issue an administrative order" for a violation.

    Reference: Minnesota Statutes 2025, Chapter 326B — Minn. Stat. § 326B.082, subd. 7

  9. 9How long is the statutory warranty period against major construction defects in a new dwelling?

    1. A. 10 years
    2. B. 1 year
    3. C. 2 years
    4. D. 5 years

    Answer: A

    Explanation: Minn. Stat. § 327A.02 provides a warranty "during the ten-year period from and after the warranty date" against major construction defects.

    Reference: Minnesota Statutes 2025, Chapter 327A — Minn. Stat. § 327A.02, subd. 1(c)

  10. 10A prime contractor has no written contract with the owner but will use subcontractors. By when must the contractor deliver the statutory pre-lien notice?

    1. A. Within 10 days after agreeing on the work
    2. B. Within 45 days after first furnishing
    3. C. Within 120 days after last furnishing
    4. D. Within one year after last furnishing

    Answer: A

    Explanation: Minn. Stat. § 514.011 requires delivery "within ten days" when there is no written contract.

    Reference: Minnesota Statutes 2025, Chapter 514 — Minn. Stat. § 514.011, subd. 1

Topics in this practice bank

These topics describe the available practice for Qualifying Builder (QB) Exam. Review the examination outline and its sources for scope and allocation details.

  • Plans and Specifications
    • Basic Plan Information
  • Energy
    • Interior Air Barrier
    • Wind Wash Barrier
    • Vapor Retarder
    • Insulation
    • Fenestration Openings
    • Mechanical and Passive Ventilation
  • Building Planning and Life Safety
    • Means of Egress
    • Stairways
    • Smoke Alarms
    • Required Exit Door
    • Wall Between House and Garage
    • Safety Glazing
    • Natural Light and Ventilation
    • Minimum Ceiling Heights
    • Replacement Windows
  • Sitework
    • Soils
    • Surveys
    • Excavation and Gopher State One Call
    • Filling and Soil Correction
    • Erosion Control
    • Backfill
    • Frost Protection
  • Footings and Foundations
    • Concrete Admixtures
    • Concrete Specification
    • Concrete Air Entrainment
    • Concrete Curing
    • Foundation Wall Design
    • Vertical Reinforcement and Anchors
    • Minimum Size Footings
    • Dampproofing and Waterproofing
    • Slab-on-grade
  • Carpentry
    • Protection Against Decay
    • Engineered Floor Systems
    • Conventional Floor Systems
    • Wall Framing
    • Engineered Roof Framing
    • Conventional Roof Framing
    • Stairs
    • Decks and Balconies
    • Chimneys and Chases
    • Structural Load Path
    • Wood Foundations
  • Roofing
    • Underlayment and Ice Barrier
    • Rolled Roofing
    • Asphalt Shingles
    • Wood Shingles and Shakes
    • Flashing
    • Roof Ventilation
  • Exterior Finishes
    • House Wraps
    • Flashing
    • Vertical Siding
    • Wood Siding
    • Aluminum and Vinyl Siding
    • Hardboard Siding
    • Wood Shakes and Shingles
    • Stucco
    • Brick Veneer
  • Foam Plastic
    • Flame Spread
    • Thermal Protection
  • Interior Finishes
    • Drywall
  • Associated Trades
    • Electrical
    • Plumbing
    • Energy
  • Safety
    • Lead
  • Fraudulent, Deceptive, or Dishonest Practices
    • License and Advertising Misrepresentation
    • Contract Misrepresentation
    • Permits and Inspections
    • Diversion of Funds
  • Residential Insurance Claims
    • Deductibles and Inducements
    • Estimates and Policy Advice
    • Post-loss Assignment and Cancellation
  • Construction Worker Classification
    • Written Contract
    • Entity, Invoices, and Payment
    • Control, Expenses, and Profit or Loss
    • Misclassification Penalties
  • Construction Contractor Registration
    • Registration Requirement
    • Registration Exemptions
  • CCLD Enforcement
    • Administrative Orders
    • Penalties and Correction
    • Subpoenas and Investigations
  • Licensing and Regulation
    • Definition and Scope
    • License Exemptions
    • Qualifying Person
    • Application and Disclosure
    • Examination Content
    • Grounds for Sanctions
    • Liability Insurance
    • License Number and Advertising
  • Statutory Warranties
    • One-, Two-, and Ten-year Periods
    • Notice and Inspection
    • Repair Offer
    • Exclusions and Modification
  • Assumed Names
    • Filing and Publication
    • Renewal and Amendment
  • Mechanic's Liens and Payment
    • Contractor Pre-lien Notice
    • Subcontractor Notice
    • Lien Statement
    • Attachment and Priority
    • Enforcement Deadline

How to use these free practice questions

Choose an answer, check the explanation, and review your progress by chapter. Practice questions and explanations are free to access without signing up.

These are independent study questions, not actual examination items. For examination requirements and official information, view Qualifying Builder (QB) Exam details.