Free Water Well Contractor Test Practice Questions
60 free questions · Answer explanations · No signup required
View examination details, outline and sourcesLoading selected examination banks…
Sample Practice Questions
Try these 10 sample questions from the Water Well Contractor Test practice bank. Each includes the answer and explanation. Continue with the interactive practice above to review the full question set.
1After final grading, how high must the top of a water-well casing extend above the finished ground surface?
2For steel casing governed by the standard table, what minimum wall thickness is specified?
- A. 0.125 inch
- B. 0.154 inch
- C. 0.188 inch
- D. 0.250 inch
3How must a new well awaiting pump installation be protected at the top?
- A. With only a downward screened vent
- B. With a watertight cap that prevents surface contamination
- C. With a loose temporary cover below grade
- D. With an unsealed hubcap-type cover
4Who must determine the applicable Missouri drilling area before choosing an area's construction standard?
- A. The well owner
- B. The well installation contractor
- C. The pump installation contractor
- D. The department laboratory
5Who is ordinarily responsible for having an abandoned water well plugged?
- A. The well installation contractor in every case
- B. The well owner, subject to the improper-construction exception
- C. The pump installation contractor in every case
- D. The department in every case
6What drainage condition is required around a completed water well?
- A. A gravel basin must hold runoff within 10 feet
- B. The casing must be below grade
- C. Water must drain away with no ponding within 10 feet
- D. A ditch must circle the casing at 5 feet
7How must adjoining sections of steel water-well casing be connected?
- A. By the solvent-weld method used for plastic joints
- B. By the mechanical-joint method permitted for plastic casing
- C. By fitting a drive shoe at the lower casing end
- D. By watertight welded or threaded joints
8Which piping and electrical connection treatment is required at a standard aboveground wellhead completion?
- A. A watertight well seal between casing and a surface-pump suction pipe
- B. A pitless adapter or unit used for a belowground connection
- C. Watertight mechanical or welded and sealed connections
- D. A one-half-inch screened vent pointed downward
Answer: C
Explanation: Aboveground connections must "Have watertight piping and electrical connections that" are mechanical or welded and sealed. The other choices are real requirements for different wellhead components or completion types.
Reference: Missouri Secretary of State: Code of State Regulations — 10 CSR 23-3.050(6)(A)2
9A contractor locates a standard bedrock well in Drilling Area 1. Which casing pair meets the area minimums?
- A. 20 feet total with 5 feet into bedrock
- B. 40 feet total with 15 feet into bedrock
- C. 60 feet total with 20 feet into bedrock
- D. 80 feet total with 30 feet into solid bedrock
10Within what period must a dry hole be plugged?
Topics in this practice bank
These topics describe the available practice for Water Well Contractor Test. Review the examination outline and its sources for scope and allocation details.
Well Siting and Groundwater Protection
- Location, drainage, casing height, and contamination setbacks
- Groundwater safeguards during construction and repair
Water Well Construction
- Casing materials, joints, installation, and boreholes
- Grout materials, cure times, and placement methods
- Multifamily, high-yield, public, and oil-or-gas-zone wells
Wellhead Completion, Disinfection, and Liners
- Wellhead protection and disinfection
- Liner materials, placement, packers, and seals
Missouri Drilling Areas
- Construction and contamination controls in Drilling Areas 1 through 13
Water Well Plugging
- Responsibility, preparation, materials, and plugging methods
How to use these free practice questions
Choose an answer, check the explanation, and review your progress by chapter. Practice questions and explanations are free to access without signing up.
These are independent study questions, not actual examination items. For examination requirements and official information, view Water Well Contractor Test details.